Construction stage of the Este by Emilia Romana complex 05.2025

The π„π¬π­πž 𝐛𝐲 𝐄𝐦𝐒π₯𝐒𝐚 π‘π¨π¦πšπ§πš complex has completed its rough construction. Here is where we have reached with the more basic activities of each of the three buildings:
π„π¬π­πžπŸ
βœ”οΈ the window frames have been installed up to floor 6
βœ”οΈ screed has been laid on the floor
βœ”οΈ plaster has been applied to the walls
βœ”οΈ the building is being thermally insulated
βœ”οΈ plaster is being applied to the facade
βœ”οΈ Electrical and plumbing installations are being worked on
π„π¬π­πž 𝟐
βœ”οΈ the window frames have been installed up to floor 4
βœ”οΈ work is being done on the facade
βœ”οΈ Electrical and plumbing installations are being worked on
π„π¬π­πž πŸ‘
βœ”οΈ the window frames have been installed up to floor 2
βœ”οΈ Electrical and plumbing installations are being worked on